Week 9 · John, foreman
Bi-folds are in and the house is fully weather-tight. Electrician starts first fix Monday. Please confirm your socket layout by Friday.
Plan · Client portal demo
This is a working demo of the kind of project portal we're proposing for E.P. Muldoon clients. Click around: switch tabs, read the site diary, approve the pending change.
Week 9 of 16. Everything is on programme.
On timeHandover due week 16
£148,000 contract + £14,100 of changes you've signed off
Extra double socket to island · £240
Monday, 8am. Electrician: Dave

Latest from site · Week 9
Bi-folds are in and the house is fully weather-tight. Electrician starts first fix Monday. Please confirm your socket layout by Friday.
Revision 3 · the line shows where we are today.
Groundworks & drainage
Walls & steels
Roof & lantern
Bi-folds & windows
First fix electrics & plumbing
Plastering
Kitchen fit
Floors & decoration
Snagging & handover
Every week, photos and a note from John.

Week 9 · John, foreman
Bi-folds are in and the house is fully weather-tight. Electrician starts first fix Monday. Please confirm your socket layout by Friday.

Week 8 · John, foreman
Lantern craned in on Tuesday, a dry day, as hoped. Roof membrane finished. Internal steel inspected by building control: passed.

Week 7 · John, foreman
Walls at full height. The brick match came up really well against the original house. Have a look at the corner when you're passing.

Week 5 · John, foreman
Found an old shared drain under the floor. Photos attached. We've applied for the build-over agreement today. See change order CO-03.
Every change is priced and signed off before work goes ahead. No surprises on the final invoice.
| Ref | Change | Price | Status |
|---|---|---|---|
| CO-01 | Upgrade to slim-frame slidersRaised Week 2 | £6,800 | Signed off |
| CO-02 | Underfloor heating to extensionRaised Week 4 | £3,900 | Signed off |
| CO-03 | Shared drain: build-over and re-routeRaised Week 5 | £3,400 | Signed off |
| CO-04 | Extra double socket to islandRaised Week 9 | £240 |
Everything about your build in one place, forever.
E.P. Muldoon's view has always been that the biggest risk to cost, quality and time is change, and the answer is communication. A portal puts that communication in writing, in one place, and in your pocket.
Nothing is left to the end of the job. You see the programme as it really stands, the money as it really stands, and a photo record of everything that gets covered up.
How we work

Start a conversation
A call with Eddie or Paul costs nothing and commits you to nothing. We'll tell you honestly whether we're the right builder for your project.